P1-11 : 150 MW
P1-11 : 150 MW Wind m/s - 7,6 (100m)
| Budgeting/ assessment of profitability | Wind measurement | Selection of local partners | Lease contracts with land owner notarial signed | Zoning plan | Wind report | Location permit & pre- contract with grid operator | EIA approval/ ornithology study |
| Detailed layout / Micrositing | Geological report | Approval aeronautical authority / military | Selection of wind turbines | Building permit | Grid connection | Wind turbines ordered |
| Completed | Continues | Not started yet |